What to measure, and which way is better.

The indicators that show how a warehouse, a production line, maintenance and quality are doing: what each one shows and how it is worked out.

Warehouse

Whether stock is where the records say, and orders leave right and on time.

Recorded by Inventory Management (WMS)
Stock record accuracy

How far the stock records can be trusted, location by location.

Locations whose count matches the recordLocations counted

Higher is betterWERC DC Measures

Picking accuracy

Orders that leave with the right items in the right quantities.

Orders picked without an errorOrders picked

Higher is betterWERC DC Measures

Dock-to-stock time

How long goods wait between arriving and being ready to use.

Time from arrival to put away and recorded, on average

Lower is betterWERC DC Measures

On-time shipments

Promises kept at the dock.

Orders shipped on timeOrders shipped

Higher is betterWERC DC Measures

Lines picked per hour

The pace of picking.

Order lines pickedPicking hours

Higher is betterWERC DC Measures

Order cycle time

How long a customer waits for an order to leave.

Time from order received to order shipped, on average

Lower is better

Stock turns

How often the stock is used up and replaced in a year.

Cost of goods sold in a yearAverage stock value

Higher is betterWork it out

Days on hand

How many days of use the stock would cover.

Average stock valueCost of goods sold per day

Lower is betterWork it out

Production

How much of the planned time makes good units, and whether the plan is kept.

Recorded by Manufacturing Execution (MES)
Overall equipment effectiveness (OEE)

The share of planned time that makes good units at the ideal speed.

Availability × performance × quality

Higher is betterISO 22400-2Work it out

Availability

The planned time the line actually runs.

Run timePlanned production time

Higher is betterISO 22400-2Work it out

Performance

How close the line runs to its ideal speed.

Ideal cycle time × units producedRun time

Higher is betterISO 22400-2Work it out

Quality ratio

Good units among all the units made.

Good unitsUnits produced

Higher is betterISO 22400-2Work it out

Total effective equipment performance (TEEP)

How much of all the hours in the period make good units.

Fully productive timeCalendar time

Higher is betterWork it out

Throughput rate

Units made for each hour of production.

Units producedProduction time

Higher is betterISO 22400-2

Schedule attainment

The planned output actually made in the period.

Units made to planUnits planned

Higher is better

Changeover time

The time between orders when nothing good is made.

Time from the last good unit of one order to the first good unit of the next

Lower is better

Manufacturing lead time

How long an order spends from release to completion.

Completion time − release time, on average

Lower is better

Output per labour hour

Units made for each hour people work.

Units producedLabour hours

Higher is better

Maintenance

How long equipment runs, how fast it is back, and how much work is planned.

Recorded by Maintenance Management (CMMS)
Mean time between failures (MTBF)

How long equipment runs between failures.

Operating timeFailures

Higher is betterISO 22400-2Work it out

Mean time to repair (MTTR)

How long a repair takes, from failure to running again.

Repair timeRepairs

Lower is betterISO 22400-2Work it out

Failure rate

Failures for every hour of operation.

FailuresOperating time

Lower is betterIEC 61703Work it out

Inherent availability

The share of time equipment can run, counting failures and repairs only.

MTBFMTBF + MTTR

Higher is betterIEC 61703Work it out

Planned maintenance percentage

Maintenance done to plan rather than after a failure.

Planned maintenance hoursAll maintenance hours

Higher is betterSMRP

Preventive maintenance compliance

Preventive work done when it was due.

Preventive work orders done on timePreventive work orders due

Higher is betterSMRP

Reactive work

Maintenance hours spent on breakdowns.

Hours of corrective work after failuresAll maintenance hours

Lower is betterSMRP

Maintenance backlog

Work waiting, in weeks of the crew's time.

Hours of work waitingCrew hours available a week

Lower is betterSMRP

Maintenance cost to replacement value

A year's maintenance against what the equipment would cost to replace.

Maintenance cost in a yearReplacement value of the assets

Lower is betterEN 15341

Quality

Units right the first time, defects per million, how capable the process is, and what poor quality costs.

Recorded by Quality Control (QMS)
First pass yield

Units right the first time, without rework.

Units good the first timeUnits produced

Higher is betterISO 22400-2Work it out

Scrap ratio

Units that cannot be saved.

Units scrappedUnits produced

Lower is betterISO 22400-2Work it out

Rework ratio

Units made twice.

Units reworkedUnits produced

Lower is betterISO 22400-2Work it out

Defective parts per million

Defective units on the scale customers often use.

Defective unitsUnits produced× 1.000.000

Lower is betterWork it out

Defects per million opportunities (DPMO)

Defects against every chance there was to make one.

DefectsUnits × opportunities per unit× 1.000.000

Lower is betterISO 13053-1Work it out

Process capability (Cp)

Whether the process spread fits the tolerance.

Upper limit − lower limit6 × standard deviation

Higher is betterISO 22514-4Work it out

Process capability index (Cpk)

Whether it fits where the process is actually centred.

Distance from the mean to the nearer limit3 × standard deviation

Higher is betterISO 22514-4Work it out

Cost of poor quality

What failures cost, against sales.

Internal and external failure costsSales

Lower is betterBS 6143-2Work it out

Complaint rate

How often customers find a problem.

ComplaintsDeliveries

Lower is better

Corrective action closure time

How long it takes to remove a cause for good.

Days from opening a corrective action to closing it, on average

Lower is better

Definitions follow the standards and associations named with each indicator. Indicators without a name beside them are worked out the same way everywhere.

Sources

  • Warehousing Education and Research Council (WERC), DC Measures, the yearly benchmarking study of warehouse and distribution metrics. werc.org
  • ISO 22400-2:2014, Automation systems and integration: key performance indicators for manufacturing operations management, Part 2: definitions and descriptions. International Organization for Standardization. iso.org
  • IEC 61703:2016, Mathematical expressions for reliability, availability, maintainability and maintenance support terms. International Electrotechnical Commission. webstore.iec.ch
  • Society for Maintenance & Reliability Professionals (SMRP), Best Practices Metrics. smrp.org
  • EN 15341:2019+A1:2022, Maintenance: maintenance key performance indicators. European Committee for Standardization (CEN).
  • ISO 13053-1:2011, Quantitative methods in process improvement: Six Sigma, Part 1: DMAIC methodology. International Organization for Standardization. iso.org
  • ISO 22514-4:2016, Statistical methods in process management: capability and performance, Part 4: process capability estimates and performance measures. International Organization for Standardization.
  • BS 6143-2:1990, Guide to the economics of quality: prevention, appraisal and failure model. British Standards Institution. knowledge.bsigroup.com

Start with the part you want to improve.